DEC-0015: Ingestion Loop Design

Status: Accepted Date: 2026-03-12 Deciders: Nexus (Human), Nexus Method Architect

Context

Ingestion is not a linear one-shot phase. Requirements are rarely complete or contradiction-free on first pass, and they evolve throughout the project as the Nexus gains understanding through working software. Two feedback mechanisms drive this evolution: the Auditor clarification loop (within ingestion) and the demo discovery loop (post-execution).

Decision

The Ingestion Loop

Ingestion consists of three roles operating in a multi-pass cycle:

  1. Analyst — elicits, understands, and formalizes requirements
  2. Auditor — validates requirements for consistency, completeness, coherence, traceability, and testability
  3. Nexus — resolves issues that only domain knowledge can answer
flowchart TD
    classDef nexus    fill:#c9b8e8,stroke:#6b3fa0,color:#1a0a2e,font-weight:bold
    classDef agent    fill:#b8d4e8,stroke:#2d6b9e,color:#0a1a2e,font-weight:bold
    classDef gate     fill:#e8d4b8,stroke:#9e6b2d,color:#2e1a0a,font-weight:bold
    classDef decision fill:#e8b8b8,stroke:#9e2d2d,color:#2e0a0a,font-weight:bold

    AN["Analyst<br/>─<br/>Produces Brief<br/>+ Requirements"]:::agent
    AU["Auditor<br/>─<br/>Five-check validation<br/>CONTRADICTION · GAP<br/>AMBIGUOUS · UNTRACED"]:::agent
    DEC{{"Issues<br/>found?"}}:::decision
    NQ["👤 Nexus<br/>─<br/>Receives one specific<br/>clarification question<br/>Provides domain answer"]:::nexus
    NC["⬡ Requirements Gate<br/>─<br/>Human gate"]:::gate

    AN  -->|"Requirements v1..N"| AU
    AU  --> DEC
    DEC -->|"No issues — PASS"| NC
    DEC -->|"Issues found"| NQ
    NQ  -->|"Answer may generate<br/>new requirements<br/>or ground truths"| AN

Every issue found by the Auditor triggers a clarification question to the Nexus — not a bounce back to the Analyst alone. The Analyst cannot resolve domain contradictions. Only the Nexus can.

Each clarification cycle is a full new pass: Analyst incorporates the answer, Auditor re-checks everything. The loop continues until the Auditor finds no issues.

The Demo Discovery Loop

Each execution cycle ends with a demo — a runnable version of the software the Nexus can explore. At Demo Sign-off, the Nexus may include new requirements or changes of mind.

When this happens, ingestion re-opens:

flowchart TD
    classDef nexus    fill:#c9b8e8,stroke:#6b3fa0,color:#1a0a2e,font-weight:bold
    classDef agent    fill:#b8d4e8,stroke:#2d6b9e,color:#0a1a2e,font-weight:bold
    classDef gate     fill:#e8d4b8,stroke:#9e6b2d,color:#2e1a0a,font-weight:bold
    classDef decision fill:#e8b8b8,stroke:#9e2d2d,color:#2e0a0a,font-weight:bold
    classDef warn     fill:#e8c8b8,stroke:#9e5a2d,color:#2e1a0a,font-weight:bold

    DEMO["👤 Nexus<br/>─<br/>Explores running software<br/>Signs off demo"]:::nexus
    DEC1{{"Changes or<br/>new requirements?"}}:::decision
    AN["Analyst<br/>─<br/>Incorporates new<br/>or changed requirements"]:::agent
    AU["Auditor<br/>─<br/>REGRESSION CHECK<br/>New reqs vs. all<br/>previously approved reqs"]:::agent
    DEC2{{"REGRESSION<br/>flags found?"}}:::decision
    NQ["👤 Nexus<br/>─<br/>Decides which<br/>requirement prevails"]:::nexus
    NC["⬡ Requirements Gate<br/>─<br/>Human gate<br/>for new increment"]:::gate
    NM["⬡ Go-Live<br/>─<br/>Human gate"]:::gate

    DEMO --> DEC1
    DEC1 -->|"No changes"| NM
    DEC1 -->|"Changes found"| AN
    AN   -->|"Updated requirements"| AU
    AU   --> DEC2
    DEC2 -->|"Clean"| NC
    DEC2 -->|"REGRESSION found<br/>always escalated"| NQ
    NQ   -->|"Decision recorded<br/>requirement superseded"| AN

This is expected behavior, not process failure. The demo is a discovery mechanism. The system is designed for it.

Auditor Flag Types

Flag Meaning
[CONTRADICTION] Two requirements conflict with each other. Both cited.
[GAP] Something in the Brief has no corresponding requirement.
[AMBIGUOUS] Requirement too vague to test or act on.
[UNTRACED] Requirement with no clear origin in the Brief or a Nexus answer.
[REGRESSION] New or changed requirement conflicts with a previously approved one. Nexus must decide which takes precedence.
[PASSED] Requirement cleared all checks.

[REGRESSION] flags are always escalated to the Nexus — never resolved silently between agents. Overriding a previously approved requirement is a conscious human decision.

Auditor Constraints

  • The Auditor does not modify requirements. It produces an audit report with flags.
  • The Analyst makes all changes in response to Auditor flags and Nexus answers.
  • Clarification questions to the Nexus must be specific and actionable — never "we found a problem," always "requirement REQ-004 states X but REQ-011 states Y — which takes precedence?"

Rationale

Why the Auditor asks the Nexus directly: Some contradictions cannot be resolved without domain knowledge the Analyst does not have. Bouncing only to the Analyst creates a false loop where the same issue resurfaces at the Requirements Gate. Direct Auditor → Nexus questions keep the loop honest.

Why demos trigger ingestion re-entry: The Nexus cannot always articulate requirements they do not yet know they have. Working software is the most effective requirements elicitation tool. Treating demo feedback as a natural re-entry point — not an exceptional case — makes the process robust to the reality of how requirements evolve.

Why regression checks are mandatory: A new requirement approved in isolation may silently invalidate work approved in a prior cycle. The Auditor is the only agent with visibility across the full requirements history. Regression checking is its unique contribution at this stage.

Consequences

  • Ingestion is a recurring activity throughout the project, not a one-time upfront phase
  • The Analyst and Auditor must always have access to the full requirements history, not just the current cycle's additions
  • [REGRESSION] flags may slow delivery when late-cycle requirement changes arrive — this is a feature, not a bug: the cost is made visible rather than hidden
  • The Methodologist may detect patterns in clarification frequency and recommend more thorough elicitation upfront (profile or process adjustment)

Alternatives Considered

Auditor escalates only to Analyst, never to Nexus: Simpler flow but domain contradictions stall indefinitely or get resolved incorrectly. Rejected for correctness.

No regression check on demo feedback: Faster, but risks silent requirement conflicts accumulating across cycles until they become expensive. Rejected for long-term correctness.

Demo feedback goes through a separate Change Request process: More formal, but introduces process weight that a Casual or Commercial project does not need. The Methodologist can add formality via profile — this decision keeps the base behavior lightweight. Rejected for premature formality.